- 5 week project delivered crucially within school Holidays
- Segregated works to allow partial use of the school for summer sport scamps.
- Committed site team willing to work weekends to aid completion and meet a tight deadline.
- Daily communication with employer’s agent and school caretaker to solve problems and deliver a scheme to surpass client’s expectations.
Project highlights
-
Duration:
5 weeks, during school closure.
-
Form of Contract:
JCT Minor Works
-
Value:
£210,000
Scope of works
- Refurbishment of existing school toilet block and installation of new heating system to school.
- Demolition and stripout of all redundant services from toilet areas and classrooms.
- Installation of new aluminum external doors, external windows suspended ceilings, flooring, and decorations.
- New specialist external soft play area installed to rear of school, allowing greater safety to Children.
- New storage to the rear of the school and safe removal of redundant storage.