Greystar, Student Accomodation

Contact us: 0114 478 3709 | hello@vformconstruction.com | online [+]

Unique service

  • Working in an occupied building with minimal disruption to tenants.
  • High Volume of works completed in an 8-week period.
  • Co-ordinating domestic and client nominated subcontractors.
  • Surveying as works progressed to identify dilapidation issues for resolution.
  • Regular communication to keep building manager informed of site issues.
  • Coordination of the construction programme to overcome the working time constraints caused by noise restrictions.

Project highlights

  • Duration:

    2 Months

  • Form of Contract:

    JCT Minor Works

  • Value:

    £450,000

Scope of works

  • Strip out of 115 bedrooms, en-suites and 31 kitchen / lounges.
  • Refurbishment of 115 bedrooms, 115 en-suites and 31 kitchen / lounges.
  • New kitchens & appliances.
  • New floor finishes & Decorations.
  • New services installation.
  • New furniture & AV installed.
  • New bathroom fittings.