  • Full Turnkey Service for Investor Clients – from project inception to completion.
  • Early Contractor involvement with Design Team, resolved design technical queries promptly, provided buildable solutions and an early start on site.
  • Prepare and agree design and remediation method statement with The Environmental Agency to build over a reclaimed site.
  • The liason with Ministry of Defence to safely remove unexploaded ordnance
  • Liason with adjacent land owners that inlcuded the East Coast Main Railway Line, Chesterfield Canal and Premier Inn Hotel.
  • Liason with Police to agree “Secure by Design” details and on site approval.

Project highlights

  • Duration:

    18 Months

  • Form of Contract:

    JCT Design & Build

  • Value:

    £4,950,000

Scope of work

  • Site remediation and piling works.
  • New build construction of 80 Nr 2 bedroom flats in 5 separate blocks.
  • External hard and soft landscaped drives, footpaths and gardens.
  • 50m Canal-side mooring and retaining walls.
  • Road & footpaths to adoptable highway standards.
  • Offsite foul, surface water drainage and attenuation design and installation to Statutory Authority standards.
  • Agree design standards and carry out regular site inspections with Zurich Building Warranty.
  • Acted as the Employer’s representative with all project stakeholders including bank funders, legal advisers, mains services installers, Local Authority departments, Statutory Authorities and Designers.